Remodel of existing 70,497 sf store.
|
*
*
|
11:00 AM
|
WalMart 986
|
Frisco
|
CO |
NOTICE IS HEREBY GIVEN that sealed bids will be received by the Owner for furnishing all labor, materials, transportation and services for the construction and/or installation of the following work: Remove approximately 27,000 SY of asphalt paving, scarify and re-compact aggregate base course, and install new asphalt paving consisting of 2.5 inches of AC surface course over 3 inches of AC base course. Mill approximately 12,200 SY of existing AC pavement and overlay with 2.5 inches of new AC pavement. Remove approximately 3,700 SF of concrete. Furnish and install sidewalk ramps, survey monuments, valley gutters, sidewalks, driveways and pavement striping per plan. Additional items of work as necessary to complete the project in accordance with the Approved Plans and Specifications.
|
*
*
|
1:00 PM
|
Arterial Street Reconstruction Southern Avenue PROJECT NO. 44-001-001
|
Mesa
|
AZ |
NOTICE IS HEREBY GIVEN that sealed bids will be received by the Owner for furnishing all labor, materials, transportation and services for the construction and/or installation of the following work: Construct approximately 3 miles of new 4x2-inch traffic signal quad-duct, complete with splice boxes and branch conduits. Furnish and install new 144-strand single mode fiber-optic (SMFO) backbone cable, 12-strand SMFO branch cables, fiber-optic splice closures, fiber terminations, video detection camera systems, CCTV cameras, upgrade traffic signal control equipment, and all appurtenant work at 16 signalized intersections located in downtown Mesa, all as indicated on the Approved Plans and Specifications.
|
*
*
*
|
1:30 PM
|
ITS Signal Conversions Phase - 3 PROJECT NO. 06-057-001
|
Mesa
|
AZ |
Pre-bid meeting is scheduled on February 25, 2010 at 3:00 PM Local Tucson Time. The project consists of placing Microseal surface treatment.
|
*
*
|
2:00 PM
|
1000801 COUNTYWIDE MICROSEALING
|
Tucson
|
AZ |
Pre-bid meeting is February 25, 2010 at 3:30 PM Local Tucson Time. The project consists of placing Chipseal and Fog Coat surface treatments.
|
*
*
|
2:00 PM
|
1000811 Countywide Chipsealing and Fog Coat
|
|
AZ |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $130,000
Architect: Darin Helsel, Precision Enviornmental Services
316-265-0012
dhelsel@precisionenvironmental.biz
|
*
*
*
|
2:00 PM
|
A-011325 Agnew Hall Asbestos Abatement
|
Hays
|
KS |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $332,000
Architect: Troy Steiner, Fort Hays State University
785-628-4437
tjsteiner@fhsu.edu
|
*
*
*
|
2:00 PM
|
A-011339 Agnew Hall Raze Building
|
Hays
|
KS |
NOTICE IS HEREBY GIVEN that sealed bids will be received by the Owner for furnishing all labor, materials, transportation and services for the construction and/or installation of the following work: Remove approximately 86,000 SY of asphalt paving, scarify and re-compact aggregate base course, and install new asphalt paving consisting of 2.5 inches of AC surface course over 3 inches of base course. Mill approximately 15,000 SY of existing AC pavement and overlay with 2.5 inches of new AC pavement. Remove and replace approximately 3,800 SF of concrete. Furnish and install sidewalk ramps, survey monuments, valley gutters, and pavement striping per plan. Additional items of work as necessary to complete the project in accordance with the Approved Plans and Specifications.
|
*
*
|
2:00 PM
|
Arterial Street Reconstruction Higley Road PROJECT NO. 44-003-001
|
Mesa
|
AZ |
A pre-bid meeting will be held on February 11th, 2010 at 1:30 PM. Sealed bids will be received by the Owner for construction of Bloom Elementary School Upgrades and Renovation.
|
*
*
*
|
2:00 PM
|
BLOOM ELEMENTARY School Upgrades and Renovation #10-87-10
|
Tucson
|
AZ |
Pre-Bid Conference will be held on February 23, 2010, at 10:00 A.M. (PDT). The approximate general quantities of selected items involved in the proposed work as described...
|
*
*
*
|
2:00 PM
|
Cargo Apron Phase II 3-06-0109-26
|
|
CA |
Sealed bids will be received by the Owner for furnishing all labor, materials, equipment and services required to install approximately two thousand six hundred sixty four (2,664) linear feet of three (3) inches of Asphalt Concrete on twelve (12) inches of Aggregate Base Course, five (5) inches of Asphalt Concrete on twelve (12) inches of Aggregate Base Course, over a twenty eight (28) foot roadway width within variable right-of-way, inclusive of all grading, storm drain, striping and signing as noted in the Plans, together with all pavement removal and replacement as necessary to complete the connection between existing roadways. A Pre-bid meeting is scheduled for 10:00 AM, MST, February 24, 2010.
|
*
*
*
|
2:00 PM
|
Construction Services for Paving and Storm Drain IFB PW-0210-IFB-0195
|
Buckeye
|
AZ |
Pre-bid conference is scheduled March 2, 2010 at 10:00 a.m. for Improvements.
|
*
*
*
|
2:00 PM
|
P10-0052 Streetscape Improvements
|
Peoria
|
AZ |
A pre-submittal conference and walk thru will be held on March 3rd 2010 at 9:00 AM. Sealed bids will be received by the Owner for Bid#149-10bw Painting Hallways at Hamilton HS.
|
*
|
2:00 PM
|
Painting Hallways-Hamilton HS Bid 149-10 bw
|
Chandler
|
AZ |
The Owner is accepting sealed bids to furnish all labor, materials, and equipment for: TAHOE PARKING LOT PROJECT #100001. Work consists of constructing a new paved parking lot approximately 275 parking spaces, including grading, curbs, light poles, irrigation sleeve, retention and related site work. Each bid shall be in accordance with the specifications. There will be Pre-Bid meeting held at 11:00 A.M. (MST), Wednesday, February 17, 2010.
|
*
*
*
|
2:00 PM
|
TAHOE PARKING LOT IFB 2972-7
|
Mesa
|
AZ |
NOTICE IS HEREBY GIVEN that sealed bids will be received by the Owner for furnishing all labor, materials, transportation and services for the construction and/or installation of the following work: Removal and installation of six new Variable Frequency Drives (VFDs). All specified downstream equipment from the VFDs shall be removed and replaced in accordance with the Approved Plans and Specifications. This includes, but is not limited to: pull boxes, wiring, wall penetrations, cable trays, and conduit.
|
*
*
|
2:30 PM
|
Brown Road Water Treatment Plant (WTP) Flocculator Variable Frequency Drive (VFD) Replacment PROJECT NO. 07-011-004
|
Mesa
|
AZ |
A pre-proposal conference will be held on 2/19/2010 at 10:00 AM. The Owner desires to contract with a qualified vendor to provide quality painting services.
|
*
|
2:30 PM
|
Contracted Painting Services RFP 10-037
|
Phoenix
|
AZ |
Notice is hereby given that the District will be receiving sealed bids for Estrella Foothills High School Athletic Storage Building Bid 10-012.
|
*
*
|
3:30 PM
|
EFHS Athletic Storage Building Bid 10-012
|
Buckeye
|
AZ |
Pre-submittal conference date is March 1, 2010 at 1:30 p.m. rfq for INTERSECTION IMPROVEMENTS.
|
*
*
|
4:00 PM
|
100399 PROFESSIONAL DESIGN SERVICES
|
Tucson
|
AZ |
|
Friday, March 12, 2010
|
Non-mandatory meeting as per addendum 2. This section specifies site preparation which consists of excavation, fill, clearing, grubbing, demolition, and disposal.
|
*
*
|
2:00 PM
|
4727GTW Sewer Treatment Plant Expansion (Phase II)
|
Calexico
|
CA |
The Owner will receive statements of qualifications for Architect Services.
|
*
|
2:00 PM
|
Architect Services RFQ 20-019
|
Avondale
|
AZ |
The purpose of this Proposal is to contract for grease interceptor repair and remodel for the District schools listed in the scope of work.
|
*
|
2:00 PM
|
Grease Interceptor Repair and Remodel RFP 008-0910
|
Phoenix
|
AZ |
The purpose of this Request for Qualifications is to evaluate offers from qualified firms, based on the evaluation criteria, to provide architectural and engineering services for the District.
|
*
|
2:30 PM
|
Request For Qualifications Architectual & Engineering Services CSDQ 10022
|
Phoenix
|
AZ |
The Owner is in the process of replacing aging traffic signal controllers throughout the City. This project consists of the City using ARRA funds to continue the replacement of controllers. This solicitation involves supply, delivery and installation of the new controllers. A Pre-Bid Conference will be held at 9:00 A.M., Local Time, February 23, 2010.
|
*
*
|
2:30 PM
|
TRAFFIC SIGNAL CONTROLLERS & CABINET REPLACEMENT 10PB063
|
Scottsdale
|
AZ |
A non-mandatory Pre-Bid Conference is scheduled for February 24, 2010, at 10:00 a.m. The scope of work for the Phase II, consists of the construction of 0.2 miles of multi-use pathways,...
|
*
*
|
3:00 PM
|
Transportation Enhancement Project, Phase II
|
Douglas
|
AZ |
SCOPE OF WORK: Including, but not limited to: On-Site development; Erosion Control; Survey; Demolition; Earthwork; Termite Control; Wet Utilities – Water, Sanitary, Storm; Dry-Utilities – Phone, Power; Asphalt Paving; Chain Link Fence, Signing & Striping; Sidewalks; Curb & Gutter; Landscape & Irrigation. Cast-In-Place Building Concrete & Reinforcement; Penetrating Sealer/Hardner; Joint Filler; Masonry: Structural Steel; Steel Joist & Decking; Miscellaneous Steel; Misc. Rough Carpentry; Dampproofing; Water Repellants; Building Insulation; Architectural Metal Roof Panels; Single-Ply Membrane Roofing; Sheetmetal & Flashing; Joint Sealants; Hollowmetal Dr/Fr/FinHrdwre; Wood Doors; Overhead Coiling Doors, Unit Skylights; Cement Stucco; Metal Stud Framing/GWB; Ceramic Tile; Acoustical Ceiling; Resilient Flooring; Polymer Flooring; Painting; Plastic & SS Wall Panels; Signage; Toilet Accessories; Dock Equipment; Refrigeration Installation; Fire Sprinkler Syst., Plumbing; HVAC, Electrical.
|
*
*
|
5:00 PM
|
Costco Tucson New Warehouse
|
Tucson
|
AZ |
Scope of Work: New Gas Station – Including, but not limited to: Pad Ready Site, Storm Drainage, Oil/Water Inteceptor, Concrete; Slabs, Bases and Equipment Pads, Joint Sealants; CMU or Stone Veneer; Painting; Signage; Fire Extinguishers; Misc. Specialties; Controller Unit Installation; Installation of three Underground Fuel Storage Tanks; Fuel Islands; Canopy System; installation of Fuel Handling Equipment, Fuel Piping, Gasoline Dispensers (8), Testing, and Electrical w/ Lighting.
|
*
*
|
5:00 PM
|
Costco Tucson, AZ New Gas Station
|
Tucson
|
AZ |
We are currently bidding all sub scopes for a 7,000 SF remodel of a former carpet warehouse to a retail center. We will demo the interior and rebuild to vanilla shell. The parking lot will be demolished and enlarged. The exterior will be remodeled and enhanced. We welcome bids from all subs. Please email shane@coppernailconstruction.com to get instructions on how to get the plans.
|
|
5:00 PM
|
Plaza 2235
|
Phoenix
|
AZ |
|
Monday, March 15, 2010
|
New Traffic Signal.
|
*
*
*
|
2:00 PM
|
83RD AVE AND WASHINGTON ST TRAFFIC SIGNAL
|
Tolleson
|
AZ |
The Owner invites interested and qualified Architectural Firms and/or Teams to submit a written Statement of Qualifications to provide Architectural Services, including Engineering and Specialty Design Services, relating to the proposed Arizona Stadium: North End-Zone Expansion. This is a qualifications-based selection process. Neither design proposals nor fee proposals are desired or will be accepted at this time.
|
*
|
5:00 PM
|
Arizona Stadium North End-Zone Expansion RFQ 09-8902
|
Tucson
|
AZ |
|
Tuesday, March 16, 2010
|
INVITATION TO BID
Your company is invited by Catamount Constructors to bid the following:
Havasu Inlet Repairs
Needles CA
*Bids are due by: Tuesday March 16th @ 12:00 Noon MST
This project includes the following scopes of work; Earthwork, Clear and Grub, Dewatering, Erosion and Sediment Control, Steel Sheetpile, Misc. Metals and Gates, Rip Rap, Concrete, and Concrete Pipe, Electrical. PLEASE FOLLOW BID FORMS
Bidding Status: Please Check One and Fax to 303.670.0762
No: ______ Yes: ______ Scopes of Work Performed: _________________
Make sure to fill out all information* Thank You!
Company Name: __________________________________Contact:________________
Shipping Address (No P.O. Boxes): __________________________________________
Phone: _______________Fax: _______________ Email:_________________________
Please contact:
Tom Saunders Janenne Acierno
- 303.679.4283 303.679.4260
- (Fax) 303.670.0762 (Fax) 303.670.0762
tsaunders@catamountconstructors.com jacierno@catamountconstructors.com
|
|
12:00 PM
|
Havasu Inlet Repairs
|
Needles
|
CA |
The Owner invites the submittal of a Statement of Qualifications ("SOQ") for CMAR Services from qualified firms ("Respondents") properly licensed in the State of Arizona.
|
*
|
1:00 PM
|
CMAR Services for District Wide Energy Upgrade RFQ #SUSD 01-1-2010
|
Sanders
|
AZ |
It is the District’s intent to secure providers for engineering services as needed for additions and improvement to existing schools, and other engineering services as required by the District. The qualified firms are to provide engineering services from inception through final acceptance, including but not limited to all documents necessary for consultation, design, and/or preparation of specifications, and contract documents for projects approved by the governing board.
|
*
|
1:00 PM
|
RFQ 10-04-15 Engineering Services
|
Tucson
|
AZ |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $44,540
Architect: Don Schultz, Division of Facilities Management
785-291-3992
don.schultz@da.ks.gov
|
*
*
*
|
2:00 PM
|
A-011224 Salina Equipment Storage Building Reroof
|
Salina
|
KS |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $39,500
Architect: Don Schultz, Division of Facilities Management
785-291-3992
don.schultz@da.ks.gov
|
*
*
*
|
2:00 PM
|
A-011229 El Dorado Area Crew Building Reroof
|
El Dorado
|
KS |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $173,000
Engineer: John Fulkerson, P.E., Bucher, Willis & Ratliff Corporation
785-827-3603
jfulkerson@bwcorp.com
|
*
*
*
|
2:00 PM
|
A-011291 Park Street/South Campus Drive Improvements
|
Hays
|
KS |
The Owner requires the following material at the approximate quantities at various locations in order to perform 2010 annual pavement crack sealing program.
|
*
|
2:00 PM
|
ANNUAL PAVEMENT CRACK SEALING PROJECT B-04-10-C004
|
Nogales
|
AZ |
The Owner is requesting Bids from licensed contractors to provide all materials and labor for the installation of new Sally Port doors and the removal of the old ones. A pre-bid meeting will be held on-site on Friday March 5th, 2010 at 10:00 am.
|
*
|
2:00 PM
|
Jail Sally Port Door Replacement 2010-06
|
Flagstaff
|
AZ |
The Owner is soliciting Statement of Qualifications from qualified firms to provide services for the Loop 303 Outfall Drainage System Design (Woodlands Ave. to Gila River), FCD 2010C002. The project will include open channels, culverts, and storm drains. The contract will include civil engineering analysis, modeling and design, landscape architectural design, surveying, topographical mapping, utility locating services, and geotechnical services. A pre-submittal conference will be held on March 2nd, 2010 from 11:00 AM to 12:00 PM.
|
*
|
2:00 PM
|
Loop 303 Outfall Drainage System Design RFQ, FCD 2010C002
|
|
AZ |
Communications Cable Replacement.
|
*
*
|
3:00 PM
|
C1015 Phase 3 Design Services
|
|
AZ |
Pre-proposal conference is scheduled March 4, 2010 at 11:00 a.m. Local AZ Time. LANDSCAPE MAINTENANCE.
|
*
|
4:00 PM
|
100437 LANDSCAPE MAINTENANCE
|
Tucson
|
AZ |
|
Wednesday, March 17, 2010
|
Tours will start at 9:00 A.M. at the construction site on Wednesday, February 17, 2010 and Wednesday, March 3, 2010. Project consists of construction of a bridge mounted pump structure, and more as listed...
|
*
*
|
10:00 AM
|
C 0559 South Recharge Phase 1
|
|
AZ |
Questions will be received until 2:00 PM on
March 10, 2010.The selected firm will provide professional engineering services for design...
|
*
*
|
2:00 PM
|
Design Widening 2010-010
|
Tucson-Oracle Junction-Globe Highway
|
AZ |
The Owner is seeking proposals for the rehabilitation and/or development of all or part of city-owned residential property. The site consists of five historic residential structures. An informational meeting will be held on Monday, December 14, 2009 at 3:00 p.m.
|
*
*
|
2:00 PM
|
REHABILITATION OF HISTORIC RESIDENTIAL STRUCTURES AND REDEVELOP VACANT PROPERTY RFP HRSRFP0001-1010
|
Phoenix
|
AZ |
The Owner is seeking bids from qualified firms for renovation of existing classroom space. A Mandatory Pre-Bid Conference will be held on March 3, 2010 at 10:00 AM (MST).
|
*
*
|
3:00 PM
|
Northwest Campus Science Hybrid Learning Lab Bid No. B10/9710
|
Tucson
|
AZ |
The Owner is accepting sealed bids to furnish all labor, materials, and equipment for: LC 371 TANDBERG LAB REMODEL, PROJECT NUMBER 100041 Work consists of the remodeling of the existing language lab into new conference room and individual tutor rooms. There will be Pre-Bid Meeting held at 9:30A.M. (MST), Tuesday, March 9, 2010. Bidders shall be required to sign in.
|
*
*
|
3:30 PM
|
LC 371 TANDBERG LAB REMODEL IFB 2979-7
|
Scottsdale
|
AZ |
Pre-bid conference is scheduled for Monday, February 22, 2010 at 10:00 A.M., Local AZ Time. Recreation Center Improvements.
|
*
*
*
|
4:00 PM
|
100360 ARRA Cherry Avenue Recreation Center Improvements
|
Tucson
|
AZ |
|
Thursday, March 18, 2010
|
Pre-bid Conference is scheduled for March 4, 2010 at 11:00 a.m. Local AZ Time. MST. Provide & deliver a Precast Concrete Comfort Station (Restroom).
|
*
|
11:00 AM
|
IFB 1001415 Precast Concrete Comfort Station (Restroom)
|
Tucson
|
AZ |
Sealed bids will be received by the Owner for Hollinger Elementary Upgrades and Renovations. A Pre-Bid meeting will be held on February 22nd 2010 at 10:00 AM.
|
*
*
|
1:00 PM
|
Hollinger Elementary Upgrades and Renovations 10-89-10
|
Tucson
|
AZ |
The Project consists of Removing Existing Pavement and affecting all other pertinent removals; Placing New Pavement, Sidewalk, Curb & Gutter, Sidewalk Ramps, Driveways, ...
|
*
*
*
|
2:00 PM
|
2010000291 Avenue 3E Reconstruction and Street Pavement Replacement
|
Yuma
|
AZ |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $450,000
Architect: Fred Abercrombie, Abercrombie Architects, P.A.
785-483-6383
fred@cfabercrombie.com
|
*
*
*
|
2:00 PM
|
A-011211 Rarick Hall Roof Replacement
|
Hays
|
KS |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $615,000
Architect: Clark Simpson, PBA Architects
316-262-7400
clarks@pbawichita.com
|
*
*
*
|
2:00 PM
|
A-011268 Yates Hall Renovation - HVAC
|
Pittsburg
|
KS |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $610,000
Engineer: Larry Stoss, BWR Corporation
785-827-3603
lstoss@bwrcorp.com
|
*
*
*
|
2:00 PM
|
A-011290 Utility Tunnel Replacement Center of Quadrangle to Picken Hall
|
Hays
|
KS |
The Owner extends an invitation to all qualified architectural engineering firms to submit their qualifications, experience, and capabilities to provide architectural engineering services for the design and construction of miscellaneous schools and additions and improvements to existing schools outlined in the Project Description. A pre-submittal meeting will be held on March 9, 2010 beginning at 2:00 p.m.
|
*
|
2:00 PM
|
ARCHITECTURAL ENGINEERING SERVICES RFQ 10-010
|
Buckeye
|
AZ |
Supplier/contractor shall furnish all labor, material, equipment, transportation and supervision to refurbish the City Gym.
|
*
|
2:00 PM
|
City Gym Rehabilitation CDBG Project 143-10
|
San Luis
|
AZ |
Notice is hereby given that the Owner is soliciting Statements of Qualifications from Design-Build Firms to utilize the One-Step Design-Build contracting procedure for the design and construction of a Moccasin Justice Court.
|
*
*
|
2:00 PM
|
MOCCASIN JUSTICE COURT DESIGN-BUILD RFQ 10-PS-07
|
Colorado City
|
AZ |
A non mandatory Site visit is scheduled for March 10, 2010, 2:00 p.m. The Owner requests competitive proposals from qualified firms to design and install a solar hot water generating system.
|
*
*
|
2:00 PM
|
PW-1023 Solar Hot Water Generating Systems
|
Sierra Vista
|
AZ |
The purpose of this RFP is to enter into a contract and secure pricing with a qualified vendor (a third party power provider) to provide a privately-owned solar photovoltaic (PV) energy system with a capacity to be determined by the vendor and to sell the electricity output to the District.
|
*
|
2:00 PM
|
SOLAR PHOTOVOLTAIC SYSTEM INSTALLATION RFP 10-003
|
Buckeye
|
AZ |
A pre-bid conference is scheduled at 10:00 a.m. on March 2, 2010. The Owner will receive bids from Licensed Contractors to construct 3 new single family residences (SFR) located on the New Pascua Reservation. The scope of work includes the demolition and removal of the existing units, building the pad, utilities, and construction of the unit as described in this bid package.
|
*
*
|
3:00 PM
|
3 Tribal Replacement Homes Project
|
Tucson
|
AZ |
The Owner extends an invitation to qualified civil engineering firms to submit their qualifications, experience, and capabilities to provide civil engineering services for the design and construction of miscellaneous schools, offsite improvements, land investigations and additions and improvements to existing schools outlined in the Project Description. A pre-submittal conference will be held on March 9, 2010 at 3:00 p.m.
|
*
|
3:00 PM
|
Civil Engineering Services RFQ 10-011
|
Buckeye
|
AZ |
Sealed Bids will be received by the Owner for the Southside Improvement Project, Project No. 03-08004, Bid Number: 2010-28. Work will include removal and replacement of concrete sidewalk/curb/gutter/driveways, asphalt pavement reconstruction and mill/overlay, landscaping, irrigation, installation of street lights, trash receptacles, benches and bicycle racks. A pre-bid meeting will beheld on March 9th, 2010 at 9:00 am.
|
*
*
|
3:00 PM
|
SOUTHSIDE IMPROVEMENT PROJECT 2010-28
|
Flagstaff
|
AZ |
The Owner is inviting your firm to submit a Statement of Qualifications (SOQ) for providing Construction Manager at Risk (CMAR) Services for the Scudder Park Improvements Project.
|
*
|
4:30 PM
|
CMAR SCUDDER PARK IMPROVEMENTS
|
Tempe
|
AZ |
|
Friday, March 19, 2010
|
|
*
|
12:00 AM
|
Daulat Medical Suites A & B
|
Laughlin
|
NV |
A pre-submittal conference will be held on Tuesday, March 9, 2010, at 8:30 a.m. The Owner is seeking a qualified Construction Manager at Risk (CMAR) to provide design phase assistance and complete construction services for approximately 7.5 miles of new roadway, Sonoran Boulevard, from 23rd Avenue to Cave Creek Road. Also included in this project is construction of approximately 5 miles of a Shared Use Path in proximity of the roadway.
|
*
|
12:00 PM
|
Sonoran Blvd: 23rd Avenue To Cave Creek Road - CMAR ST85100335-1010
|
Phoenix
|
AZ |
A pre?bid conference will be held at 9:00 a.m. local Tucson time, March 4, 2010. This project is to refurbish the 400 Hz ground power system...
|
*
*
|
2:00 PM
|
10108852 Ground Power System
|
Tucson
|
AZ |
A pre-bid meeting will be held on February 26th 2010 at 9:00 AM. Scope: Provide all labor, materials, and equipment to furnish and install spray applied polyurethane foam roof and protective coating system, including existing roof preparation, flashing repairs, deck repairs and miscellaneous repairs and materials to the Main Roof Area. Roof size is approximately 15,500 square feet.
|
*
|
2:00 PM
|
Foam Roofing Services IFB 10-124
|
Phoenix
|
AZ |
|
Monday, March 22, 2010
|
Notice is hereby given that the Owner invites sealed Requests for Qualifications for Architectural and Engineering Services for a new Multi-Purpose Building & Administrative Rooms and possibly including renovations to existing space. There will be a pre-proposal meeting and site visits at 10:00 am MST on March 16, 2010.
|
*
|
10:00 AM
|
ARCHITECTURAL ENGINEERING SERVICES RFQ 2010-01
|
Rimrock
|
AZ |
A Pre-submittal conference is scheduled on Friday, March 5, 2009 at 1:00 pm local time. The Owner wishes to enter into a contract with a qualified firm or firms to perform Construction Management at Risk Services as outlined in this document for a one year period with one year extensions not to exceed a five year period. The District will have the sole discretion to extend this contract for years 2 through 5.
|
*
|
11:00 AM
|
Construction of Transportation/Maintenance and Warehouse Facilities and Administrative Offices CMR 10-005
|
Avondale
|
AZ |
The Owner is requesting a Statement of Qualifications for:
DESIGN/BUILD SERVICES for the MIDDLE/JUNIOR HIGH SCHOOL FIELD PROJECT RFQ #10-03.
|
*
|
11:00 AM
|
DESIGN/BUILD SERVICES for the MIDDLE/JUNIOR HIGH SCHOOL FIELD PROJECT RFQ #10-03
|
Lakeside
|
AZ |
A Prebid Conference will be held on March 10, 2010 at 9:00 a.m. This project consists of approximately 1/4 mile of roadway widening.
|
*
|
2:00 PM
|
601862 Roadway Widening
|
Las Vegas
|
NV |
A Mandatory Prospective Bidders' Conference will be held on March 15, 2010 at 10:00 AM. Competitive sealed Bids will be received by the Owner for Solicitation Number: PW2010-01, Project Number: S6003 Solicitation Title: Alley Paving, Phase II
|
|
3:00 PM
|
Alley Paving, Phase II PW2010-01
|
Fountain Hills
|
AZ |
No pre-bid conference will be held for this project. This project consists of construction of sanitary sewers, including but not limited to furnishings and installation of manholes,...
|
*
*
|
3:00 PM
|
SS2690 Mockingbird Area Sewers
|
Lake Havasu City
|
AZ |
|
Tuesday, March 23, 2010
|
Sealed Bids will be received by the Owner for Baseline Road Bridge Over Western Canal Project 5402991. The proposed work will consist of the DEMOLITION, REMOVAL AND REPLACEMENT OF A BRIDGE OVER THE SALT RIVER PROJECT’S WESTERN CANAL AND ROADWAY IMPROVEMENTS together with associated work. There will be a pre-bid meeting on Wednesday, March 10, 2010, at 10:00 a.m.
|
*
*
|
10:00 AM
|
Baseline Road Bridge Over Western Canal Project 5402991
|
Tempe
|
AZ |
A PRE-BID CONFERENCE WILL HELD ON MARCH 9, 2010 AT 9:00 A.M. This project consists of asphalt milling, construction of asphalt-rubber concrete pavement,...
|
*
|
11:00 AM
|
2010-030 Asphalt-Rubber Overlay
|
|
AZ |
There will be a pre-bid meeting on February 24, 2010 at 10:30 a.m. The scope for this Phase 3 includes installation of 2,000± LF of new 42-64" and 6,000± LF of new 66" diameter pipe using mostly...
|
*
*
*
|
2:00 PM
|
1000295 Santa Cruz Interceptor Phase 3
|
Tucson
|
AZ |
A Prebid Conference will be held on March 8, 2010 at 9:30 a.m. The work consists of the replacement of approximately 3,850 square feet of concrete sidewalk, including....
|
*
|
2:00 PM
|
601874-10 Sidewalk Repairs
|
Las Vegas
|
NV |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $200,000
Architect: Don Schultz, Division of Facilities Management
785-291-3992
don.schultz@da.ks.gov
|
*
*
*
|
2:00 PM
|
A-011297 Reroof Vogel Building
|
Kansas City
|
KS |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: 240,000
Engineer: John Ladson, Bartlett & West, Inc.
785-272-2252
john.ladson@bartwest.com
|
*
*
*
|
2:00 PM
|
A-011320 Kaw Valley State Park Boat Ramp
|
Topeka
|
KS |
Bridge Deck Rehabilitations (ARRA) work will include Bridge Deck Preparation; Methacrylate Treatment; Bridge Deck Repair; Methacrylate; Polyester Concrete Overlay; and various other miscellaneous items. A pre-bid conference for this project will be held on Friday, January 29th, 2010 at 2:00 p.m. Local Time.
|
*
|
2:00 PM
|
Bridge Deck Rehabilitations ARRA ST85110079-1010
|
Phoenix
|
AZ |
A pre-bid conference will be held at 10:00 am local time, Tuesday, March 9th 2010. Sealed bids will be received by the Owner for construction of Bid 09-10-17 Crouch Mesa EMS Facility.
|
*
*
|
2:00 PM
|
Crouch Mesa EMS Facility Bid 09-10-17
|
Aztec
|
NM |
A pre-bid meeting will be held on March 9, 2010 at 10:00 a.m. The Owner is requesting bids to perform Phase II of the implementation of the Golden Valley Improvement District’s Supervisory Control and Data Acquisition (SCADA) system, Invitation for Bids (IFB) No. 10-B-03. The proposed Work consists of, but is not limited to: replacement of antenna(e); addition of radio equipment, processor, sensor head, level transmitters and pressure transmitters; as well as associated demolition, excavation and equipment start-up.
|
*
*
|
2:00 PM
|
GOLDEN VALLEY WATER DISTRIBUTION SCADA – PHASE II, IFB 10-B-03
|
Kingman
|
AZ |
It is the intent of this agreement to provide the Owner with Long Line Pavement Marking Services on an as needed, where needed basis. Please see attachment for proposed roadways and estimated quantities. This includes but is not limited to painted center lines, lane lines, edge lines and holding bars, as identified by the Owner's Representative.
|
*
|
2:00 PM
|
IFB COS10-023 Pavement Marking Services
|
Surprise
|
AZ |
Sealed bids will be received by the Owner for construction of Miller,Grijalva, & Maldonado Elementary Schools-Kitchen Renovations 10-91-10. The Pre Bid will be held at 1:00 PM on 3/10/2010.
|
*
*
|
2:00 PM
|
Miller,Grijalva, & Maldonado Elementary Schools-Kitchen Renovations 10-91-10
|
Tucson
|
AZ |
The Owner is seeking qualified bids for Purchase, Removal and Installation of 4 New Roof Top HVAC Units and 1 New Split System A/C Unit.
|
*
|
2:00 PM
|
Purchase, Removal and Installation of 4 New Roof Top HVAC Units and 1 New Split System A/C Unit IFB NO. F10-02-22
|
Holbrook
|
AZ |
The Owner requests competitive sealed bids from qualified firms furnishing all labor, materials, and equipment...
|
*
*
|
2:00 PM
|
PW-0910 KINO ROAD TURN LANE
|
Sierra Vista
|
AZ |
A pre-bid conference will be held on March 10th 2010 at 9:00 am. Scope of work: Remove existing and install new roof at the District Office for the Maintenance and Transportation buildings. Re-roof Tempe High School buildings Q, Z and repair roofing on building M as per the plans and specifications.
|
*
*
|
2:00 PM
|
Re-roof at District Office and Tempe HS IFB 09-008
|
Tempe
|
AZ |
A Pre Bid will be held 3/11/2010 at 1:00 PM. Sealed bids will be received by the Owner for Cholla High Magnet School Reroofing 10-95-10.
|
*
*
|
3:00 PM
|
Cholla High Magnet School Reroofing 10-95-10
|
Tucson
|
AZ |
The Owner is soliciting Qualifications & Experience (Responses) from persons or firms capable of providing residential rehabilitation services. A pre-submittal conference is scheduled on March 9, 2010 at 3:00 p.m.
|
*
|
3:00 PM
|
Housing Rehab Program NR0-912-2743
|
Chandler
|
AZ |
A MANDATORY prebid meeting will be held at the site on March 10, 2010 at 10:00 AM at the site. The Owner will receive sealed bids from General Contractors for awarding of a contract to furnish all labor and materials, plant, transportation, and services required for the SELECTIVE DEMOLITION at the 15th Street Elementary School at 839 E. 15th Street, Douglas Arizona.
|
*
*
|
3:00 PM
|
SELECTIVE DEMOLITION
|
Douglas
|
AZ |
Pre-bid conference is March 10, 2010 at 9:00 a.m. Local AZ time. INTERSECTION IMPROVEMENTS.
|
*
*
|
4:00 PM
|
100350 Ft. Lowell/Campbell Intersection Improvements
|
Tucson
|
AZ |
|
Wednesday, March 24, 2010
|
A pre-bid conference will be held on Wednesday, March 10, 2010, at 10:00 a.m. Sealed bids will be received by the Owner for STREET RENOVATION - SLURRY SEAL Solicitation Number: 2010-4106-0221.
|
*
|
10:30 AM
|
STREET RENOVATION – SLURRY SEAL 2010-4106-0221
|
Gilbert
|
AZ |
New Fuel Center. Please do not contact the owner or architect with questions.
|
*
*
|
12:00 PM
|
Smith's 473 Fuel Center
|
Fort Mohave
|
AZ |
LETTING: 03-24-10 Page 1 of 4
KANSAS DEPARTMENT OF TRANSPORTATION
510032071 U075-070 KA 1201-02 ARRA-A120(102)
___________________________________________________________________________
NOTICE TO CONTRACTORS and CONTRACT PROPOSAL
1. The Secretary of Transportation of the State of Kansas [Secretary] will
receive sealed proposals from prequalified contractors for construction,
improvement, reconstruction, or maintenance work in the State of Kansas,
said work known as Project No. U075-070 KA 1201-02 ARRA-A120(102)
[Project]. The general scope of the project is:
GRADING, BRIDGE & SURFACING. LOCATION IS REPLACEMENT OF
BRIDGE(035), 0.28 MILES N OF THE K-268 JCT IN OSAGE COUNTY.
NET LENGTH IS 0.254 MILES.
|
*
*
*
|
1:00 PM
|
GRADING, BRIDGE & SURFACING
|
Osage County
|
KS |
Contract: 510032091
Project/Federal Project Number: K018-081 KA 0410-03 /ARRA-A041(003)
County:
RILEY
Project Description: GRADING, BRIDGES & SURFACING, STATE TIE: K018-081 KA 0410-06
Plan Sheets
| Plan Sheets #2
| Plan Sheets #3
| Plan Sheets #4
Project Ties: 510032111 KA 0410-06
Pre-Bid Conference Required for this project
1060 Sheets in Small Plans 647 Sheets in X-Section
Working Days: CCD KDOT Construction Office:
Starting Dates - Earliest: Lates
LETTING: 03-24-10 Page 1 of 4
KANSAS DEPARTMENT OF TRANSPORTATION
510032091 K018-081 KA 0410-03 ARRA-A041(003)
___________________________________________________________________________
NOTICE TO CONTRACTORS and CONTRACT PROPOSAL
1. The Secretary of Transportation of the State of Kansas [Secretary] will
receive sealed proposals from prequalified contractors for construction,
improvement, reconstruction, or maintenance work in the State of Kansas,
said work known as Project No. K018-081 KA 0410-03 ARRA-A041(003)
[Project]. The general scope of the project is:
GRADING, BRIDGES & SURFACING. LOCATION IS K-18 FROM WALNUT
ST. (OGDEN) NE TO 0.1 MI W WILDCAT CR RD IN RILEY COUNTY.
NET LENGTH IS 1.980 MILES. STATE TIED WITH K018-081 KA
0410-06.
t:
|
*
*
|
1:00 PM
|
GRADING, BRIDGES & SURFACING, STATE TIE: K018-081 KA 0410-06
|
Riley County
|
KS |
Contract: 510032011
Project/Federal Project Number: 046 N 0482-01 /ARRA-N048(201)
County:
JOHNSON
Project Description: MILLING AND OVERLAY, STATE TIE: 46 N 0498-01 & 46 N 0483-01
Plan Sheets
Project Ties: 510032031 N 0483-01
Project Ties: 510032031 N 0483-01, 510032051 N 0498-01
28 Sheets in Small Plans
Working Days: 25 KDOT Construction Office:
Starting Dates - Earliest: Latest:
LETTING: 03-24-10 Page 1 of 4
KANSAS DEPARTMENT OF TRANSPORTATION
510032011 046 N 0482-01 ARRA-N048(201)
___________________________________________________________________________
NOTICE TO CONTRACTORS and CONTRACT PROPOSAL
1. The Secretary of Transportation of the State of Kansas [Secretary] will
receive sealed proposals from prequalified contractors for construction,
improvement, reconstruction, or maintenance work in the State of Kansas,
said work known as Project No. 046 N 0482-01 ARRA-N048(201)
[Project]. The general scope of the project is:
MILLING AND OVERLAY. LOCATION IS MERRIAM: MERRIAM DR FROM
JOHNSON DR TO SHAWNEE MISSION PARKWAY IN JOHNSON COUNTY.
NET LENGTH IS 0.650 MILES. STATE TIED WITH 46 N 0498-01 &
46 N 0483-01.
|
*
|
1:00 PM
|
MILLING AND OVERLAY, STATE TIE
|
Johnson County
|
KS |
Contract: 510032051
Project/Federal Project Number: 046 N 0498-01 /ARRA-N049(801)
County:
JOHNSON
Project Description: MILLING AND OVERLAY, STATE TIE: 46 N 0482-01 & 46 N 0483-01
Plan Sheets
Project Ties: 510032011 N 0482-01
Project Ties: 510032011 N 0482-01, 510032031 N 0483-01
28 Sheets in Small Plans
Working Days: 35 KDOT Construction Office:
Starting Dates - Earliest: Latest:
LETTING: 03-24-10 Page 1 of 4
KANSAS DEPARTMENT OF TRANSPORTATION
510032051 046 N 0498-01 ARRA-N049(801)
___________________________________________________________________________
NOTICE TO CONTRACTORS and CONTRACT PROPOSAL
1. The Secretary of Transportation of the State of Kansas [Secretary] will
receive sealed proposals from prequalified contractors for construction,
improvement, reconstruction, or maintenance work in the State of Kansas,
said work known as Project No. 046 N 0498-01 ARRA-N049(801)
[Project]. The general scope of the project is:
MILLING & OVERLAY. LOCATION IS MERRIAM: 55TH ST FROM
MERRIAM DR TO SWITZER RD IN JOHNSON COUNTY. NET LENGTH IS
0.690 MILES. STATE TIED WITH 46 N 0482-01 & 46 N 0483-01.
|
*
|
1:00 PM
|
MILLING AND OVERLAY, STATE TIE: 46 N 0482-01 & 46 N 0483-01
|
Johnson County
|
KS |
LETTING: 03-24-10 Page 1 of 4
KANSAS DEPARTMENT OF TRANSPORTATION
510032051 046 N 0498-01 ARRA-N049(801)
___________________________________________________________________________
NOTICE TO CONTRACTORS and CONTRACT PROPOSAL
1. The Secretary of Transportation of the State of Kansas [Secretary] will
receive sealed proposals from prequalified contractors for construction,
improvement, reconstruction, or maintenance work in the State of Kansas,
said work known as Project No. 046 N 0498-01 ARRA-N049(801)
[Project]. The general scope of the project is:
MILLING & OVERLAY. LOCATION IS MERRIAM: 55TH ST FROM
MERRIAM DR TO SWITZER RD IN JOHNSON COUNTY. NET LENGTH IS
0.690 MILES. STATE TIED WITH 46 N 0482-01 & 46 N 0483-01.
|
*
*
|
1:00 PM
|
MILLING AND OVERLAY, STATE TIE: 46 N 0482-01 & 46 N 0483-01
|
Johnson County
|
KS |
LETTING: 03-24-10 Page 1 of 4
KANSAS DEPARTMENT OF TRANSPORTATION
510032011 046 N 0482-01 ARRA-N048(201)
___________________________________________________________________________
NOTICE TO CONTRACTORS and CONTRACT PROPOSAL
1. The Secretary of Transportation of the State of Kansas [Secretary] will
receive sealed proposals from prequalified contractors for construction,
improvement, reconstruction, or maintenance work in the State of Kansas,
said work known as Project No. 046 N 0482-01 ARRA-N048(201)
[Project]. The general scope of the project is:
MILLING AND OVERLAY. LOCATION IS MERRIAM: MERRIAM DR FROM
JOHNSON DR TO SHAWNEE MISSION PARKWAY IN JOHNSON COUNTY.
NET LENGTH IS 0.650 MILES. STATE TIED WITH 46 N 0498-01 &
46 N 0483-01.
Contract: 510032031
Project/Federal Project Number: 046 N 0483-01 /ARRA-N048(301)
County: JOHNSON
Project Description: MILLING AND OVERLAY, STATE TIE: 46 N 0498-01 & 46 N 0482-01
Plan Sheets
Project Ties: 510032011 N 0482-01
Project Ties: 510032011 N 0482-01, 510032071 N 0498-01
29 Sheets in Small Plans
Working Days: 30 KDOT Construction Office:
Starting Dates - Earliest: Latest:
|
*
|
1:00 PM
|
MILLING AND OVERLAY, STATE TIE: 46 N 0498-01 & 46 N 0482-01
|
Johnson County
|
KS |
LETTING: 03-24-10 Page 1 of 4
KANSAS DEPARTMENT OF TRANSPORTATION
510032031 046 N 0483-01 ARRA-N048(301)
___________________________________________________________________________
NOTICE TO CONTRACTORS and CONTRACT PROPOSAL
1. The Secretary of Transportation of the State of Kansas [Secretary] will
receive sealed proposals from prequalified contractors for construction,
improvement, reconstruction, or maintenance work in the State of Kansas,
said work known as Project No. 046 N 0483-01 ARRA-N048(301)
[Project]. The general scope of the project is:
MILLING AND OVERLAY. LOCATION IS MERRIAM: MERRIAM DRIVE
FROM 57TH STREET TO ANTIOCH ROAD IN JOHNSON COUNTY. NET
LENGTH IS 0.900 MILES. STATE TIED WITH 46 N 0498-01 & 46 N
0482-01.
|
*
*
|
1:00 PM
|
MILLING AND OVERLAY, STATE TIE: 46 N 0498-01 & 46 N 0482-01
|
Johnson County
|
KS |
The Owner is accepting Statements of Qualifications from firms to provide a Professional Engineering...
|
*
|
2:00 PM
|
2010-014 Professional Engineering
|
|
AZ |
The purpose of this Request for Proposal is to solicit qualified vendors who can provide general construction services and all required materials per drawings and specifications.
|
*
*
|
2:30 PM
|
Shade Structures For Mesquite Elementary School RFP C-004-0910
|
Yuma
|
AZ |
PRE-BID CONFERENCE WILL NOT BE HELD FOR THIS PROJECT. BID OPENING IS AT 3:00 P.M., ON MARCH 24, 2010. Surface Treatment.
|
*
|
3:00 PM
|
2010-029 Rubberized Bituminous Surface Treatment
|
|
AZ |
The Owner is accepting sealed bids for preventative maintenance on streets and roadways within the City limits which includes sealing surface cracks and rejuvenating pavement sections with a slurry or fog seal. There will not be a pre-bidders conference held, however all inquiries are due in writing no later than March 10, 2010, 5:00 P.M.
|
*
|
3:00 PM
|
Microseal Fog and Slurry Program EN 10-031
|
Avondale
|
AZ |
The Owner is looking for a qualified, licensed and bonded roofing contractor. Contractor shall provide services, labor and materials to reroof 12 residential units in the Old Pascua Yaqui Community.
|
*
|
3:00 PM
|
Roofing Bid Invitation for 12 SFR Roof Replacements
|
Tucson
|
AZ |
A PRE-BID CONFERENCE WILL NOT BE HELD. The work consists of asphalt milling...
|
*
*
|
3:00 PM
|
TT322 Asphalt Rubber Overlay 2009-047
|
|
AZ |
A Pre-Bid Conference will be held March 17, 2010 at 3:00 PM, Arizona Time.
Replace existing electrical distribution equipment, lighting fixtures, raceways and wires, junction boxes, and outlets which have ...
|
*
|
4:00 PM
|
10-C-003 Pool Filtration Building Electrical Replacement
|
Bullhead City
|
AZ |
|
Thursday, March 25, 2010
|
Owner is seeking experienced contractors to perform miscellaneous construction and repair services ...
|
*
|
10:00 AM
|
2010-032 Roadway Stabilization and Paving 2010-033
|
|
AZ |
Pre-submittal conference is Thursday, March 4, 2010 at 9:00 AM Local Tucson Time. (SOQ) for a range of Remodeling and Construction services...
|
*
*
|
1:00 PM
|
1001442 JOC REMODELING AND CONSTRUCTION
|
|
AZ |
This contract shall be for furnishing all labor, materials, transportation and services for the construction and/or installation of the following work: Provide all piping, 12-inch waterline, all appurtenances and site restoration work required to upgrade Pressure Reducing Valve No. 28 and connect a new waterline from the existing waterline at Desert Well No. 12 to an existing main in Ellsworth Road, in accordance with the Contract Documents.
|
*
*
|
1:00 PM
|
Upgrade Pressure Reducing Valve No. 28 & Connect Desert Well No. 12 to Falcon Field Zone 09-915-001
|
Mesa
|
AZ |
This contract shall be for furnishing all labor, materials, transportation and services for the construction and/or installation of the following work: Utility locating and potholing by Vacuum Extraction (City Wide).
|
*
|
1:30 PM
|
UTILITY LOCATING AND POTHOLING BY VACUUM EXTRACTION 07-904-003
|
Mesa
|
AZ |
Prebid Conference will be held on March 9, 2010 at 11:00 a.m. Site visit is March 12, 2010 at 8:00 a.m. Project includes site work.
|
*
*
|
2:00 PM
|
601828-09 Glendale Peak Communication Site Replacement
|
Las Vegas
|
NV |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $33,054
Architect: Don Schultz Division of Facilities Management
785-291-3992
don.schultz@da.ks.gov
|
*
*
|
2:00 PM
|
A-011242 Wichita West Cone Reroof
|
3200 East 45th Street N
|
KS |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $24,397
Architect: Don Schultz Division of Facilities Management
785-291-3992
don.schultz@da.ks.gov
|
*
*
|
2:00 PM
|
A-011243 Pratt Cone Reroof
|
Pratt
|
KS |
A Mandatory Pre-Bid Conference will be held at 1:00 P.M., Local Time, March 9, 2010 at the site. Scope: Removal of Black Hills Tank Dam and restoration of existing site in the preservation.
|
*
*
|
2:00 PM
|
BLACK HILLS TANK DAM REMOVAL 10PB076
|
Scottsdale
|
AZ |
NOTICE IS HEREBY GIVEN that sealed bids will be received by the Owner for furnishing all labor, materials, transportation and services for the construction and/or installation of the following work: includes construction of new storm drain inlet and outlet structures, new storm drain culverts, plain and grouted riprap construction, infield grading improvements along the south side of Runway 4L-22R, acrylic copolymer dust palliative application, and appurtenant work, all as indicated on the Approved Plans and Specifications.
|
*
*
|
2:00 PM
|
Runway Safety Area Improvements Storm Drain Safety Improvements PROJECT NO. 06-078-001
|
Mesa
|
AZ |
The Owner is seeking proposals from qualified firms for Architectural Services on an as needed basis.
|
*
|
3:00 PM
|
Architectural Services P10/9707
|
Tucson
|
AZ |
The Owner is soliciting sealed bids for
CIRCUIT BREAKER OVERHAUL.
|
*
|
3:00 PM
|
C1018 Circuit Breaker Overhaul
|
|
AZ |
Sealed proposals will be received by the Town of Cary at the office of the Engineering Department, 316 N. Academy Street, Cary, North Carolina until March 25, 2010 at 3 p.m. and thereafter immediately opened and read publicly for the furnishing of materials, labor, and equipment for the construction of High House Road Waterline Extension Project, Project No. WT1165. (Approximate quantities involved are or brief project description is) as follows:
± 1395 LF of 12-inch DIP Waterline
± 20 LF Bore and Jack 20” Casing Pipe
± 1150 LF Remove & Replace Standard concrete sidewalk
All associated clearing, erosion control, traffic control and construction operations.
Plans, Specifications and Contract documents may be seen at http://townofcary.contractorsplanroom.com upon registering online, at the office of the Director of Engineering, Cary Town Hall; the Associated General Contractors, Raleigh office; McGraw-Hill Construction Dodge, Raleigh office; the North Carolina Institute of Minority Economic Development, Durham office; and the Cary office of CDC News; after February 25, 2010. The Town of Cary is not responsible for bidders relying on incomplete bid documents.
Copies of Plans, Specifications and Contract documents may be obtained after February 25, 2010 online at http://townofcary.contractorsplanroom.com at vendor pricing. These documents may also be obtained at the office of the Engineering Department, 316 N. Academy Street, Cary, North Carolina upon non-refundable payment of $30 per set in cash or check. A postage and handling charge of $10 will be added for any items which are mailed. Please direct all inquiries to Jamie Bissonnette, P.E. at (919) 380-2760 or jamie.bissonnette@townofcary.org
Contractors offering a proposal on this project must be licensed to do the specified type of contracting in the State of North Carolina. A Town of Cary Privilege License in accordance with North Carolina General Statutes is required for award of the project. All bids must include a non-collusive affidavit.
Each proposal shall be accompanied by a bid deposit in the amount of not less than five percent (5%) of the amount of the bid in the form and subject to the conditions provided in the Instruction to Bidders.
The Town of Cary reserves the right to reject any or all proposals.
|
*
*
|
3:00 PM
|
High House Road Waterline Extension Project
|
Cary
|
NC |
The Owner is seeking to enter into an Agreement with a CONTRACTOR to furnish all labor, materials, services, supervision, tools, equipment, licenses, and permits necessary to complete the work described herein.
|
*
|
3:00 PM
|
Price Road Rehab - ARRA Project ST0-745-2838
|
Chandler
|
AZ |
The Owner is seeking bids from licensed and qualified contractors to provide construction and installation of general renovations and correction of City Code violations to buildings located on Western Avenue between Dysart Road and Central Avenue, including but not limited to installation or repair of windows, doors, paint, exterior wall treatments, awnings, overhangs and signs. In addition work includes the abatement of asbestos as more fully set forth in the scope of work. A MANDATORY Pre-bid conference will be held on March 3rd, 2010 at 10:30 am.
|
*
|
3:00 PM
|
Western Avenue Business Renovation Project NFS 10-049
|
Avondale
|
AZ |
A job walk will be held on Thursday, March 11th, 2010 at 10:00 A.M. Local Time. Provide all material, labor, equipment and transportation.
|
*
|
4:00 PM
|
10-49-FAC-05 Fry Wash Drainage Improvement
|
Sierra Vista
|
AZ |
Pre-proposal conference date is Monday, February 8, 2010 at 9:00 A.M., Local AZ Time. Filter Replacement and Maintenance of Air Handling Units.
|
*
|
4:00 PM
|
100340 Filter Replacement and Maintenance
|
Tucson
|
AZ |
A Non-Mandatory pre-submittal meeting will be held on March 16, 2010 at 1:30 PM, MST. The Owner invites interested and qualified Engineering firms to submit a written Statement of Qualifications to provide Engineering Services relating to the proposed new Arizona Health Sciences Center (AHSC) Transformer Yard Expansion Project. This is a qualifications-based selection process. Neither design proposals nor fee proposals are required at this time.
|
*
|
5:00 PM
|
AHSC Transformer Yard Expansion Project Engineering Services RFQ S501028
|
Tucson
|
AZ |
|
Friday, March 26, 2010
|
This project includes two separate Pre-Engineered Metal Buildings (PEMB) on the same site: a single story Administration Building of 12,000 square feet and a two story Facilities and Sign Shop Building of 13,250 square feet. Scope of work includes engineering and design of PEMB as described in the specifications and drawings, interior partitions, ceilings, floor finishes, mechanical, plumbing, and electrical building systems. Utilities are limited to inside of building and five feet outside of perimeter. No landscape or hard-scape.
|
*
*
|
11:00 AM
|
Gila County Public Works Bid No. 110109-1
|
AZ
|
AZ |
The project will realign the roadway curve and guardrail.
ADOT will only accept bids from prequalified contractors purchasing bid documents directly from ADOT.
|
*
|
11:00 AM
|
H571801C SYSTEM PRESERVATION-RECONSTRUCTION
|
Town of Prescott Valley
|
AZ |
The work consists of constructing concrete floors underneath the existing bridge (structure # 1320) over Martinez Creek.
ADOT will only accept bids from prequalified contractors purchasing bid documents directly from ADOT.
|
*
|
11:00 AM
|
H749601C MINOR BRIDGE REHABILITATION
|
north of the city of Congress
|
AZ |
There is a mandatory site walk through scheduled for Thursday, February 25, at 12:30 p.m. local time. Sealed bids will be received by the Owner for the PUBLIC WORKS COMPLEX ROADS/SHOP BUILDING, BID NO. 110309-1.
|
*
*
|
11:00 AM
|
PUBLIC WORKS COMPLEX ROADS/SHOP BUILDING PROJECT 110309-1
|
Globe
|
AZ |
Sealed bids will be received by the Owner for BID NO. 110109-1, COUNTY FACILITIES AND SIGN SHOP. The Architect will hold a Pre-Bid Conference at the site, at 10:00 a.m. local time on Thursday, February 25, 2010. Attendance at this Conference by prospective Bidders is mandatory.
|
*
*
|
11:30 AM
|
COUNTY FACILITIES AND SIGN SHOP BID 110109-1
|
Globe
|
AZ |
The Owner is seeking a qualified Construction Manager at Risk (CMAR) to provide design phase assistance and complete construction services for the Arcadia Drive Drainage Improvement Project. A pre-submittal conference will be held on Friday, March 12, 2010, at 9:00 a.m., local time.
|
*
|
12:00 PM
|
ARCADIA DRIVE DRAINAGE IMPROVEMENTS CM@RISK
|
Phoenix
|
AZ |
The work to be done consists in general of providing traffic control & construction area signs and crack sealing for phase 1...
|
*
|
2:00 PM
|
4983 RESURFACING PROJECT
|
|
CA |
THE OWNER IS ADVERTISING FOR AN OFFICIAL REQUEST FOR QUALIFICATIONS FOR CM@ RISK PRE-CONSTRUCTION AND CONSTRUCTION SERVICES - MAINTENANCE AND WAREHOUSE FACILITIES Request for Qualification (RFQ) #10-06-10. This construction management project is known as the Construction of the New Maintenance/Warehouse Facilities and shall include: Building of new Maintenance/Warehouse Facilities of potential Pre-Engineered Buildings (depending on the final Guaranteed Maximum Price and schedule). The facilities are to be a total of approximately 12,000 gross square feet.
|
|
2:00 PM
|
CM@ RISK MAINTENANCE AND WAREHOUSE FACILITIES RFQ 10-06-10
|
Maricopa
|
AZ |
The purpose of this proposal is to create a contract to have a qualified vendor provide HVAC Equipment and Outsourced Services.
|
*
|
2:00 PM
|
HVAC Equipment and Outsourced Services IFB 09-04-14
|
Fort Thomas
|
AZ |
A pre-bid conference is scheduled for March 10th 2010 at 10:30 am. It is the intent of the District to obtain the services of a qualified firm or individual , to procure the services to re-roof buildings 200, 300 and 400 at McClintock High School as indicated on the plans and specifications with building 100 being an "add alternate".
|
*
*
|
2:00 PM
|
Re-roof McClintock High School IFB 09-007
|
Tempe
|
AZ |
Contractor shall provide all labor, material, equipment, services and procedures to remove partial or entire existing shingle and/or built-up roofs then furnish and install new shingle roof over-lay, shingle roofing, built-up roofs, torch-down, rubberized, and Peel & Stick rolled roofing; and provide roofing repair for Senior Housing Sites and Scattered Sites single family houses, on an as-needed basis. These are federally-funded services; therefore HUD and Davis-Bacon requirements apply.
|
*
|
2:00 PM
|
Roofing Replacement & Repair IFB 10-126
|
Phoenix
|
AZ |
The work to be done includes but is not limited to roadway excavation and earthwork,....
|
*
*
|
2:30 PM
|
4044X Reconstruction of Baughman Road
|
|
CA |
A Mandatory Pre-Bid Conference will be held at 9:00 A.M., Local Time, March 11, 2010. Scope: The expansion of the water campus advanced water treatment facility (AWT) to 20 million gallons per day (mgd) of product water capacity. The work includes improvements to the water campus, expansion of the microfiltration facilities, expansion of the reverse osmosis facilities, new AWT operations building, expansion of the recharge well facilities and installation of reuse water blending facitlities.
|
*
|
3:00 PM
|
ADVANCED WATER TREATMENT FACILITY EXPANSION 10PB069
|
Scottsdale
|
AZ |
The Owner desires to contract with a responsible firm or firms to provide heating, ventilation, and air conditioning (HVAC) services to its members on a job order contracting (JOC) basis. The work under an awarded contract(s) will include minor construction, repair, rehabilitation, and alteration services for a wide variety of statewide educational, other government and not for profit agencies.
|
*
|
3:00 PM
|
Job Order Contracting for Heating Ventilation Air Conditioning RFQ 10C-0326
|
Kingman
|
AZ |
|
Monday, March 29, 2010
|
A Pre-Submittal Conference is scheduled for March 15, 2010 at 2:00 P.M. LOCAL TIME. The Owner is requesting a Statement of Qualifications for: CONSTRUCTION MANAGER SERVICES for the Athletic Facilities PROJECT RFQ # WR 2010-144.
|
*
|
2:00 PM
|
CONSTRUCTION MANAGER SERVICES RFQ # WR 2010-144
|
Ft. Defiance
|
AZ |
|
Tuesday, March 30, 2010
|
The District is looking for a Labor and material quote for re-roof the JDPS Classroom Buildings.
|
*
|
10:00 AM
|
Jack Daley Primary School Re-Roof Phase II
|
Thatcher
|
AZ |
A Pre Bid will be held 3/11/2010 at 3:00 PM. Sealed bids will be received by the Owner for Cholla Magnet High School Exterior Improvements 10-94-10.
|
*
*
|
10:30 AM
|
Cholla Magnet High School Exterior Improvements 10-94-10
|
Tucson
|
AZ |
A Prebid Conference will be held on March 11, 2010 at 10:00 a.m. The work includes but not limited to excavating...
|
*
|
2:00 PM
|
601840 Pulverize, Pave and Slurry ARRA-0003(130)
|
Las Vegas
|
NV |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $314,000
Engineer:Kelly Conway, Brack & Associates Consulting Engineers
785-271-6644
|
*
*
*
|
2:00 PM
|
A-011219 Kelce Hall HVAC, Electrical & Fire Safety Modifications
|
Pittsburg
|
KS |
A Pre Bid meeting will be held on 3/17/2010 at 9:00 AM. Sealed bids will be received by the Owner for construction of Santa Rita HS Stadium Lighting Renovations 10-96-10.
|
*
*
|
2:00 PM
|
Santa Rita HS Stadium Lighting Renovations 10-96-10
|
Tucson
|
AZ |
The work under this section shall consist of furnishing and installing 16,232 new traffic signs (43,615 SF of Type IV retro-reflective sheeting and 10,933 SF of Type IX retro-reflective sheeting) on existing sign posts, remove and salvage 11,232 traffic signs, remove and recycle 275 traffic signs, replace 1,530 illuminated street name signs and various miscellaneous items as indicated with plans, specifications, bid documents and as required for the proper execution of the work.
|
*
|
2:00 PM
|
Sign Reflectivity & Retrofit ST85140031-1010
|
Phoenix
|
AZ |
|
Wednesday, March 31, 2010
|
Prebid Conference will be held on March 9, 2010 at 1:00 p.m. Site visist March 16, 2010 at 9:00 a.m. Including site work.
|
*
*
|
2:00 PM
|
601877 Communications Site Improvements
|
Las Vegas
|
NV |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $34,411
Architect: Don Schultz Division of Facilities Management
785-291-3992
don.schultz@da.ks.gov
|
*
*
|
2:00 PM
|
A-011227 Belleville Geodesic Dome Reroof
|
Belleville
|
KS |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $36,411
Architect: Don Schultz Division of Facilities Management
785-291-3992
don.schultz@da.ks.gov
|
*
*
|
2:00 PM
|
A-011228 US 24 - US 81 Geodesic Dome Reroof
|
Concordia
|
KS |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $30,915
Architect: Don Schultz Division of Facilities Management
785-291-3992
don.schultz@da.ks.gov
|
*
*
|
2:00 PM
|
A-011230 Waverly Geodesic Dome Reroof
|
Waverly
|
KS |
The project consists of construction of a 12-foot wide concrete pathway with two-foot wide decomposed granite shoulders, including an underpass at Chaparral Road, storm water pump station, retaining wall, landscaping and irrigation, and related incidental items. A Pre-Bid Conference will be held at 9:00 A.M., Local Time, March 9, 2009.
|
*
|
2:00 PM
|
INDIAN BEND WASH MULTIUSE PATH 10PB056
|
Scottsdale
|
AZ |
To provide all labor, materials, equipment, and supplies necessary to construct approximately 1,950 lineal feet of 6" and 8" diameter water pipelines and other water system appurtenances...policy that bid documents must be purchased through Metropolitan Domestic Water in order to bid the job.
|
*
*
|
2:00 PM
|
M-09-003 WINDEMERE STREET INTERCONNECTION
|
Tucson
|
AZ |
|
Thursday, April 1, 2010
|
Scope: Replace and Upgrade as noted various doors, door frames and door hardware District wide. Please advise district of intent to bid.
|
*
|
10:00 AM
|
District Wide Door & Door Hardware Replacement RFP
|
Thatcher
|
AZ |
A pre-submittal conference will be held on March 16, 2010 at 12:30 p.m. Owner is seeking experienced engineering consultants to perform Construction Administration services.
|
*
|
10:00 AM
|
TT178, Ellsworth Road 2010-031
|
|
AZ |
Presolicitation, intension is to issue a solicitation with a requirement to Repair the Building Exterior.
|
*
|
1:00 PM
|
P0610JPF10001REPAIR BUILDING EXTERIOR
|
SAN DIEGO
|
CA |
This acquisition is an unrestricted Best Value Request for Proposal (RFP), open to both large and small business concerns. WORK CONSISTS of building a new Air Aviation Support Facility (AASF) and Aircraft Rescue and Firefighting Facility (ARFF) of permanent type construction. Documents will be issued on or about February 22nd, 2010.
|
|
2:00 PM
|
NEW MEXICO ARMY NATIONAL GUARD ARMY AVIATION SUPPORT FACILITY W912PP-10-R-0014
|
Santa Fe
|
NM |
Work consists of constructing a new parking lot approximately 500 parking spaces, including grading, asphalt paving, concrete curbing and gutters, parking lot lighting, pavement striping and landscaping. There will be a Pre-Bid meeting held at 9:00 A.M. (MST), Wednesday, March 17, 2010. Bidders shall be required to sign in.
|
|
2:00 PM
|
NEW PARKING LOT AT ESTRELLA MOUNTAIN COMMUNITY COLLEGE IFB 2974-7
|
Avondale
|
AZ |
The Owner is accepting statements of qualifications from qualified firms (Engineer) for Engineering Services consisting of the design of improvement to the City’s water distribution and sewer collections systems.
|
*
|
2:00 PM
|
On-Call Engineering Water/ Sewer Projects 2010
|
Scottsdale
|
AZ |
Sealed Bids will be received by the Owner for the Route 66 Urban Trail Landscape Project. Project consists of landscape, irrigation, pedestrian benches, bike racks, and a steel pedestrian shade structure adjacent to a portion of historic Route 66.
|
*
*
|
3:00 PM
|
Route 66 Urban Trail Landscape Project Bid 2010-35
|
Flagstaff
|
AZ |
The Owner is inviting your firm to submit a Statement of Qualifications (SOQ) for providing Construction Manager at Risk (CMAR) Services for the Johnny G. Martinez Water Treatment Plant Security Improvements Project.
|
*
|
4:30 PM
|
JOHNNY G. MARTINEZ WTP SECURITY IMPROVEMENTS PROJECT 3203501
|
Tempe
|
AZ |
|
Friday, April 2, 2010
|
The proposed work includes milling and replacing asphaltic concrete pavement...
ADOT will only accept bids from prequalified contractors purchasing bid documents directly from ADOT.
|
*
|
11:00 AM
|
H658001C PAVEMENT PRESERVATION
|
EAST OF DOUGLAS
|
AZ |
The work consists of extending five existing concrete box culverts.
ADOT will only accept bids from prequalified contractors purchasing bid documents directly from ADOT.
|
*
|
11:00 AM
|
H690601C SYSTEM ENHANCEMENT - SAFETY IMPROVEMENTS
|
ORACLE JUNCTION – FLORENCE HIGHWAY
|
AZ |
Additional work includes pavement markings, and other related items.
ADOT will only accept bids from prequalified contractors purchasing bid documents directly from ADOT.
|
*
|
11:00 AM
|
H768201C PAVEMENT PRESERVATION
|
FLAGSTAFF NORTH OF I-40
|
AZ |
The Owner is seeking a qualified Construction Manager at Risk (CMAR) to provide design phase assistance and complete construction services for the Cactus Park Police Precinct Replacement. A pre-submittal conference will not be held.
|
*
|
12:00 PM
|
CACTUS PARK POLICE PRECINCT REPLACEMENT CM@RISK
|
Phoenix
|
AZ |
The Owner is seeking a qualified consultant team to provide architectural and engineering services for the Cactus Park Police Precinct Replacement. Services may include programming, design, and possible construction administration services. A pre-submittal conference will not be held.
|
*
|
12:00 PM
|
Cactus Park Precinct Replacement Design Services
|
Phoenix
|
AZ |
The Owner is seeking a qualified Design-Build Team (DB Team) to provide design-build services for the design and construction modifications for the Taxiway A intersections project located at Phoenix Goodyear Airport (GYR). A pre-submittal conference will be held on Tuesday, March 23, 2010, at 10:00 a.m., local time.
|
*
|
12:00 PM
|
Taxiway A Intersections At Goodyear Airport - RFQ AV41000062-1010
|
Phoenix
|
AZ |
Contractor shall provide all labor, materials, equipment, and transportation required to perform Single-ply Roofing services for the Administrative Building of the Salt River Service Center. Apre-bid meeting will be held on Tuesday March 22nd, 2010 at 9:00 am.
|
*
|
2:00 PM
|
Single-Ply Roofing Services - Salt River Service Center IFB 10-147
|
Phoenix
|
AZ |
|
Monday, April 5, 2010
|
The facility will consist of multiple buildings on a single site.
|
*
*
|
2:00 PM
|
W912PL-10-R-0002 New Border Patrol Station
|
Ajo
|
AZ |
|
Tuesday, April 6, 2010
|
The Owner extends an invitation to interested and qualified firms or individuals to submit formal sealed qualifications to provide Construction Manager at Risk design phase services and construction phase services as described herein.
|
*
|
10:00 AM
|
ESTRELLA TO TOWERS JAIL CHILLED WATER LOOP CONVERSION CM@R
|
Phoenix
|
AZ |
Scope of work: Work will include concrete Sidewalk, 179 Water Meter Relocations, and miscellaneous removals and relocations of fences, mailboxes, plants, landscaping etc. No Pre-Bid Conference will be held.
|
*
*
|
2:00 PM
|
South Phoenix Village Phase II Sidewalk Improvements-CDBG ND30070275-1010
|
Phoenix
|
AZ |
|
Thursday, April 8, 2010
|
A non-mandatory pre-bid conference will be held Monday March 23, 2010 2:00 pm. The Owner hereby invites vendors to submit bids on the following: Bid # PW09/10/006 1891 Courthouse Roof Rehabilitation Project.
|
|
11:00 AM
|
Courthouse Roof Rehabilitation Project Bid PW09/10/006
|
Florence
|
AZ |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $675,000
Architect: David Riffel, Howard & Helmer Architecture
316-634-1111
driffel@howardandhelmer.com
|
*
*
*
|
2:00 PM
|
A-011304 Grubbs Hall Renovation
|
Pittsburg
|
KS |
NOTE: All contractors bidding as the prime bidder on this project must be pre-qualified with Division of Facilities Management to bid this project. For instructions on prequailifcation go to http://www.da.ks.gov/fp/contractor/default.htm
Budget: $177,000
Architect: Jeff Sherrard, Howard & Hilmer Architecture
316-634-1111
sherrard@howardandhelmer.com
|
*
*
*
|
2:00 PM
|
A-011305 Kelce Center Restroom Renovation
|
Pittsburg
|
KS |
The Owner is seeking sealed qualification Submittals for Engineering Services for the East Buckeye Park & Ride Facility.
|
*
|
2:00 PM
|
Engineering for Park and Ride Facility RFQ CD-0210-RFQ-0196
|
Buckeye
|
AZ |
A non-mandatory pre-bid conference will be held Monday March 22, 2010 9:00 am. The Owner hereby invites vendors to submit bids on the following: Bid # PW09/10/007 McCartney Road & Overfield Road Traffic Signal.
|
|
2:00 PM
|
McCartney Road & Overfield Road Traffic Signal Bid PW09/10/007
|
Florence
|
AZ |
|
Friday, April 9, 2010
|
The work consists of up-grading storm water pump stations by constructing various improvements.
ADOT will only accept bids from prequalified contractors purchasing bid documents directly from ADOT.
|
*
*
|
11:00 AM
|
H726301C RESTORATION/REHAB/RESURFACE
|
Phoenix Urbanized Area
|
AZ |
The proposed work consists of widening southbound Loop 101 to construct auxiliary traffic lanes and includes...
ADOT will only accept bids from prequalified contractors purchasing bid documents directly from ADOT.
|
*
|
11:00 AM
|
H748801C MAJOR WIDENING H748901C
|
City of Peoria
|
AZ |
Contractor shall provide all labor, materials, equipment, and transportation required to perform foam roofing services at the Union Hills Service Center EMD Building. A Pre-bid Conference will be held on Tuesday, March 23, 2010 at 9:00 a.m.
|
*
|
2:00 PM
|
Foam Roofing Services - EMD Building at Union Hills Service Center IFB 10-146
|
Phoenix
|
AZ |
A Contractor’s and Subcontractor’s Pre-Bid Conference will be held on March 15, 2010 at 10:00 AM (PST). Scope of work includes but is not limited to installation of the new posts for the new shade structures (structure to be galvanized steel).
|
*
|
2:00 PM
|
Two New Shade Structures
|
El Centro
|
CA |
|
Monday, April 19, 2010
|
Pre-bid Conference is scheduled at 9:00 AM, Arizona Time, on March 31, 2010. Opportunity, residential development.
|
*
|
5:00 PM
|
P10-0047 SOQI Residential Development
|
Peoria
|
AZ |
Pre-bid Conference is scheduled is scheduled March 31, 2010 @ 9:00 AM, Arizona Time. Opportunity for residential development.
|
*
|
5:00 PM
|
P10-0050 SOQI Residential Development
|
Peoria
|
AZ |
|
Friday, April 23, 2010
|
The work consists of widening two AASHTO Type IV precast girder bridges, earthwork, pavement removal, ...
ADOT will only accept bids from prequalified contractors purchasing bid documents directly from ADOT.
|
*
|
11:00 AM
|
H710401C CAPACITY ADDITIONS - MAJOR WIDENING
|
west of the Town of Picacho
|